PMP, Introduction to Project Procurement Management

Process Group PMBOK Knowledge Area Process Why? (inputs) How? (tools and techniques) What? (outputs)
           
Planning 12.1 Procurement Planning
  • Scope statement
  • Product description
  • Procurement resources
  • Market conditions
  • Other planning outputs
  • Constraints
  • Assumptions
  • Make-or-buy analysis
  • Expert judgment
  • Contract type selection
  • Procurement management plan
  • Statements of Work
Planning 12.2 Solicitation Planning
  • Procurement management plan
  • Statements of work
  • Other planning outputs
  • Standard forms
  • Expert judgment
  • Procurement documents
  • Evaluation Criteria
  • Statement of work updates
Executing 12.3 Solicitation
  • Procurement documents
  • Qualified seller lists
  • Bidder conferences
  • Advertising
  • Proposals
Executing 12.4 Source Selection
  • Proposals
  • Evaluation criteria
  • Organizational policies
  • Contract negotiation
  • Weighting system
  • Screening system
  • Independent estimates
  • Contract
Executing 12.5 Contract Administration
  • Contract
  • Work results
  • Change requests
  • Seller invoices
  • Contract change control system
  • Performance reporting
  • Payment system
  • Independent estimates
  • Correspondence
  • Contract changes
  • Payment requests
Closing 12.6 Contract Closeout
  • Contract documentation
  • Procurement audits
  • Contract file
  • Formal acceptance and closure